Dambov, Ilija and Dambov, Risto (2023) Construction of the pipeline trench for MHEC. XIV Стручно советување со меѓународно учество: Технологија на подземна и површинска експлоатација на минерални суровини Подекс – Повекс ’23 (14).
Text
9. Trud - Ilija Dambov - 2. I. Dambov, R. Dambov, PODEKS- 2023.pdf Download (2MB) |
Abstract
In this paper, the effects and some mining parameters that have a direct influence on a canal
for laying a pipeline are given. During the construction of the canal the necessity for analysis and review
of the applied drilling and blasting parameters has arisen, from the aspect of the resulting effects and
blasting costs.
The construction, that is, the drilling and blasting of the canal, is for a small hydropower plant for the
needs of the investor.These are special blastings that need to be well controlled in order to achieve
efficiency and good results.
Keywords: Blasting, effects, drilled holes, trench blasting canal, special blastings
Item Type: | Article |
---|---|
Subjects: | Engineering and Technology > Civil engineering Engineering and Technology > Materials engineering Engineering and Technology > Mechanical engineering |
Divisions: | Faculty of Natural and Technical Sciences |
Depositing User: | Risto Dambov |
Date Deposited: | 18 Sep 2024 08:29 |
Last Modified: | 18 Sep 2024 08:29 |
URI: | https://eprints.ugd.edu.mk/id/eprint/34642 |
Actions (login required)
View Item |