T.S. 400/110 kV is located in eastern part of Macedonia and it is one of the most important substations in the
transmission network of the country since it connects the both transmission systems Macedonian and Bulgarian
via over-head transmission line Chervena Mogila. It was commissioned during the year 2010 as a part of
Macedonia – Bulgaria Power Transmission Project which introduced construction of new 400 kV
interconnection line between S/S Stip (Macedonia) and S/S Chervena Mogila (Bulgaria). Construction of new
400/110 kV S/S Stip ,near to the city Stip, was involved as part of this project. Substation is connected to
National Dispatching Centre (NDC) through SICAP PAS program which enables data transmission to and from
NDC placed in c ity o f Skopje. S ICAM P ASCC program i s used for complete control and monitoring of the
substation i.e. SCADA system of the substation. Complete software and hardware solution is product of
company Siemens. In this paper is presented the SCADA configuration in s.s. Stip its main function and
advantages gained through implementation of this contemporary solution in substation automation.

Item Type: Conference or Workshop Item (Paper)
Subjects: Engineering and Technology > Electrical engineering, electronic engineering, information engineering
Divisions: Faculty of Electrical Engineering
Depositing User: Vasilija Sarac
Date Deposited: 18 Dec 2012 14:30
Last Modified: 18 Dec 2012 14:30
URI: https://eprints.ugd.edu.mk/id/eprint/3812

Available Versions of this Item

Actions (login required)

View Item View Item